Grade: 10
        A contractor employed a certain number of men to complete a work in a certain number of days.If three more men were deployed the work would be finished two days earlier while if twelve more men were deployed it would be finished five days earlier.Find number of men deployed by the contractor
6 years ago

Answers : (1)

Sunil Raikwar
askIITians Faculty
45 Points
							Use the formula m1d1=m2d2 in such types of problems where m means no. of workers & d means no of days.
Let no. of man be x & no. of days be y, then
xy=(x+3)(y-2)
3y-2x=6........1
& xy=(x+12)(y-5)
12y-5x=60............2
Solving eq 1&2 we get x=12& y=10
Thanks and Regards
Sunil Raikwar
askIitians faculty
6 years ago
Think You Can Provide A Better Answer ?
Answer & Earn Cool Goodies


Course Features

  • 728 Video Lectures
  • Revision Notes
  • Previous Year Papers
  • Mind Map
  • Study Planner
  • NCERT Solutions
  • Discussion Forum
  • Test paper with Video Solution


Course Features

  • 731 Video Lectures
  • Revision Notes
  • Test paper with Video Solution
  • Mind Map
  • Study Planner
  • NCERT Solutions
  • Discussion Forum
  • Previous Year Exam Questions


Ask Experts

Have any Question? Ask Experts

Post Question

 
 
Answer ‘n’ Earn
Attractive Gift
Vouchers
To Win!!! Click Here for details