15. A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs. 200 for the first day, Rs. 250 for the second day, Rs. 300 for the third day, etc., the penalty for each succeeding day being Rs. 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days.

Harshit Singh , 3 Years ago
Grade 12th pass
anser 1 Answers
Pawan Prajapati

Last Activity: 3 Years ago

We can see, that the given penalties are in the form of A.P. having first term as 200 and common difference as 50. Therefore, a = 200 and d = 50 Penalty that has to be paid if contractor has delayed the work by 30 days = S30 By the formula of sum of nth term, we know, Sn = n/2[2a+(n -1)d] Therefore, S30= 30/2[2(200)+(30 – 1)50] = 15[400+1450] = 15(1850) = 27750 Therefore, the contractor has to pay Rs 27750 as penalty

Provide a better Answer & Earn Cool Goodies

Enter text here...
star
LIVE ONLINE CLASSES

Prepraring for the competition made easy just by live online class.

tv

Full Live Access

material

Study Material

removal

Live Doubts Solving

assignment

Daily Class Assignments


Ask a Doubt

Get your questions answered by the expert for free

Enter text here...