Mayank Jain
Last Activity: 13 Years ago
Let the day taken by C alone be n
so in one day work done by C=1/n
Time taken by A to do the same work = n+9 days
so in one day work done by A=1/n+9
Also A and B can together do the work in same time as C
so work done in one day by A and B together = work done by C in one day=1/n
let work done by B in one day be b
so 1/n=b+(1/n+9)
so b=9/n(n+9)
Hence B takes n(n+9)/9 days to finish the work alone.
According to Question days taken by A alone = days taken by B alone +5
so n+9=n(n+9)/9+5
solving this n2=36 and n=6 days
Hence A alone can do the job in n+9=6+9=15 days time
Please approve if correct.