Velocity-time graph of a particle moving in a straight line is as 10 shown in figure. Mass of the particle is 20 kg. What is the Work done by all the forces in KJ acting on the particle in time interval between t = 0 to t = 10 s? (A) 5KJ (B) 8KJ (C) 6KJ (D) 3KJ PLS EXPLAIN!!!........my ans is c......but given ans is d..WHY???

 Velocity-time graph of a particle moving in a straight line is as 10 shown in figure. Mass of the particle is 20 kg. What is the Work done by all the forces in KJ acting on the particle in time interval between t = 0 to t = 10 s?


velocity-time-graph


 


        (A)     5KJ

        (B)     8KJ

        (C)     6KJ

        (D)     3KJ
PLS EXPLAIN!!!........my ans is c......but given ans is d..WHY???

Grade:9

1 Answers

Aman Bansal
592 Points
12 years ago

Dear Shivam,

The formula for Work done is:

 W= F.d .Cos(theta)

where , F= Force

D= Displacement 

Cos (thete ) = angle between the displacement and force applied.

And we know F= m.a ;m=mass and a = acceleration 

Total work done = work done is 0-5sec + workdone in 5-10s

Thus you will get total work done = 3 KJ.

Best Of luck

Cracking IIT just got more exciting,It s not just all about getting assistance from IITians, alongside Target Achievement and Rewards play an important role. ASKIITIANS has it all for you, wherein you get assistance only from IITians for your preparation and win by answering queries in the discussion forums. Reward points 5 + 15 for all those who upload their pic and download the ASKIITIANS Toolbar, just a simple  to download the toolbar….

So start the brain storming…. become a leader with Elite Expert League ASKIITIANS

Thanks

Aman Bansal

Askiitian Expert

 

 

Think You Can Provide A Better Answer ?

ASK QUESTION

Get your questions answered by the expert for free