Flag 10 grade maths> A takes 6 days less than the time taken b...
question mark

A takes 6 days less than the time taken by B to complete a piece of work. If both A and B together can complete the work in 4 days, find the time taken by B to finish the work.

Aniket Singh , 11 Months ago
Grade
anser 1 Answers
Askiitians Tutor Team

Let the time taken by B to complete the work be denoted by x days.

Since A takes 6 days less than B to complete the work, the time taken by A to complete the work will be (x - 6) days.

Now, the work done by A in 1 day is 1/(x - 6) and the work done by B in 1 day is 1/x.

When both A and B work together, their combined work rate is the sum of their individual work rates. According to the problem, together they can complete the work in 4 days. Therefore, the combined rate is 1/4.

So, the equation becomes: (1/(x - 6)) + (1/x) = 1/4.

To solve this equation, let's first find a common denominator: (x(x - 6)) on the left-hand side: [(x) + (x - 6)] / (x(x - 6)) = 1/4.

Simplifying the numerator: (2x - 6) / (x(x - 6)) = 1/4.

Now, cross-multiply to eliminate the fraction: 4(2x - 6) = x(x - 6).

Distribute both sides: 8x - 24 = x^2 - 6x.

Move all terms to one side to form a quadratic equation: x^2 - 6x - 8x + 24 = 0.

Simplify: x^2 - 14x + 24 = 0.

Now, solve this quadratic equation using the quadratic formula: x = [-(-14) ± √((-14)^2 - 4(1)(24))] / 2(1).

x = [14 ± √(196 - 96)] / 2.

x = [14 ± √100] / 2.

x = [14 ± 10] / 2.

So, x = (14 + 10) / 2 = 24 / 2 = 12 or x = (14 - 10) / 2 = 4 / 2 = 2.

Since the time taken by B must be positive and reasonable, we discard x = 2 because A would take a negative time to complete the work, which is not possible.

Thus, the time taken by B to finish the work is 12 days.

Last Activity: 11 Months ago
star
LIVE ONLINE CLASSES

Prepraring for the competition made easy just by live online class.

tv

Full Live Access

material

Study Material

removal

Live Doubts Solving

assignment

Daily Class Assignments