150 workers were engaged to finish a pieve of work in a certain number of days.Four workers dropped the second day, four more the third day and so on. IT takes 8 more days to finish the work now. Find the number of days in which the work was completed.

Soumyadeep das , 7 Years ago
Grade 10
anser 1 Answers
Arun

Last Activity: 7 Years ago

Suppose 1 worker does 1 unit work in a day
Assume 150 workers can finish the work in (n-8) days, if all workers work all the days.
Then, total work =150(n−8) ⋯(1)=150(n−8) ⋯(1)
Actually 150 workers work on day-1, 146 workers work on day-2, ... and work is completed in nn days. Therefore,
total work = 150 + 146 + ...  (nn terms)
This is an arithmetic progression with a = 150, d = -4. Therefore,
total work
=n/2[2×150+(n−1)(−4)]
=n/2[300−4n+4]
=n/2[304−4n]
=n(152−2n) ⋯(2)
=n/2[2×150+(n−1)(−4)]
=n/2[300−4n+4]
=n/2[304−4n]
=n(152−2n) ⋯(2)
From(1) and (2)
150(n−8)=n(152−2n)
75(n−8)=n(76−n)
75n−600=76n−n^2
n^2−n−600=0
(n−25)(n+24)=0
n = 25
i.e., number of days in which the work was completed = 25

Provide a better Answer & Earn Cool Goodies

Enter text here...
star
LIVE ONLINE CLASSES

Prepraring for the competition made easy just by live online class.

tv

Full Live Access

material

Study Material

removal

Live Doubts Solving

assignment

Daily Class Assignments


Ask a Doubt

Get your questions answered by the expert for free

Enter text here...