Let the day taken by C alone be n
so in one day work done by C=1/n
Time taken by A to do the same work = n+9 days
so in one day work done by A=1/n+9
Also A and B can together do the work in same time as C
so work done in one day by A and B together = work done by C in one day=1/n
let work done by B in one day be b
so 1/n=b+(1/n+9)
so b=9/n(n+9)
Hence B takes n(n+9)/9 days to finish the work alone.
According to Question days taken by A alone = days taken by B alone +5
so n+9=n(n+9)/9+5
solving this n2=36 and n=6 days
Hence A alone can do the job in n+9=6+9=15 days time
Please approve if correct.
Get your questions answered by the expert for free
You will get reply from our expert in sometime.
We will notify you when Our expert answers your question. To View your Question
Win Gift vouchers upto Rs 500/-
Register Yourself for a FREE Demo Class by Top IITians & Medical Experts Today !