150 workers were engaged to finish a job in a certain number of days. 4 workers dropped out on second day, 4 more workers dropped out on third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed

6 years ago

Answers : (1)

SAGAR SINGH - IIT DELHI
879 Points
										

 


Dear student,




Let x be the number of days in which 150 workers finish the work.


According to the given information,


150x = 150 + 146 + 142 + …. (x + 8) terms


The series 150 + 146 + 142 + …. (x + 8) terms is an A.P. with first term 146, common difference –4 and number of terms as (x + 8)



However, x cannot be negative.


x = 17


Therefore, originally, the number of days in which the work was completed is 17.


Thus, required number of days = (17 + 8) = 25


 





































Please feel free to ask your queries here. We are all IITians and here to help you in your IIT JEE preparation.


All the best.


Win exciting gifts by answering the questions on Discussion Forum. So help discuss any query on askiitians forum and become an Elite Expert League askiitian.


Now you score 5+15 POINTS by uploading your Pic and Downloading the Askiitians Toolbar  respectively : Click here to download the toolbar..


 


Askiitians Expert


Sagar Singh


B.Tech, IIT Delhi





































6 years ago
Think You Can Provide A Better Answer ?
Answer & Earn Cool Goodies
  • Complete JEE Main/Advanced Course and Test Series
  • OFFERED PRICE: R 15,000
  • View Details
Get extra R 13,000 off
USE CODE: JEE1

Ask Experts

Have any Question? Ask Experts

Post Question

 
 
Answer ‘n’ Earn
Attractive Gift
Vouchers
To Win!!! Click Here for details